Frame column surveying and layout → Column base surface plastering and leveling → Determining formwork support plan and formwork arrangement → Formwork fabrication → Load-bearing scaffolding erection → Column reinforcement binding → On-site formwork installation, correction, and reinforcement → Hidden works acceptance → Pouring frame column concrete → Concrete curing → Beam surveying and layout → Beam bottom formwork installation, correction, and reinforcement → Beam reinforcement binding → Beam side formwork installation, correction, and reinforcement → Platform slab formwork installation, correction, and reinforcement → Platform slab reinforcement binding → Beam and slab embedded parts installation → Beam and slab hidden works acceptance → Beam and slab concrete pouring → Concrete curing → Frame column surveying and layout
Concrete Formwork Construction Process